How long does it typically take to install a 2,000 sf tile roof? (in working days) | 1 day | 4% | 2-3 days | 22% | 3-5 days | 31% | 5-7 days | 18% | 7-14 days | 9% | Not sure | 13% | | | Question: How long does it typically take to install a 2,000 sf tile roof? (in working days) Top Answer (31% of 22 votes): 3-5 days.
Answer: 5-7 days Explanation: Tile roofs have multiple layers, it takes time. | Roofer Mike Inc | Answer: 2-3 days Explanation: This is a tricky question. Depending on city or state the time frame is different due to weather, permitting and inspections. In Texas its 2-5 days. There is no licensing and permits/inspections are minimal. In Florida there is a very stringent Licensing, permit, and inspection process. For a regular residential tile roof in Florida, it could take up to a month. | Phoenix Roofing & Construction Inc. | Answer: 7-14 days Explanation: because of the way most tile roofs hang on the supports below you have to take extra time to make sure they are hung the right way to seal out leaks and if the roof is pitched the will have to be hand nailed like cedar you can not use a nail guy if you do you will crack them | metal masters construction.llc |
|